PERT Charts: What They Are and How to Use Them
A PERT chart (Program Evaluation Review Technique) is a graphical tool used in project management to plan, schedule and manage tasks within a project. It is used to visualise and organise the tasks involved in a project, along with their interdependencies and critical path.
A PERT chart typically consists of a network diagram of boxes and arrows, where each box represents a task, and each arrow represents the sequence of functions. The boxes are often called nodes, and the arrows as links or paths.
The nodes are usually numbered and labelled to identify the tasks they represent. They also contain the task name, duration, start and finish dates, and the resources assigned. The links or arrows between nodes indicate the dependencies between tasks, with the direction of the arrow indicating the order in which tasks must be completed.
A PERT chart also includes critical path analysis, a method used to determine the sequence of tasks that must be completed on time to complete the project within the given deadline. The critical path is the most extended sequence of tasks that must be completed to finish the project on time.
Overall, a PERT chart is a valuable tool for project managers to plan and monitor their projects' progress and identify potential delays or roadblocks.
Use of PERT chart in project management
PERT charts are used extensively in project management for various purposes, including:
- Planning and Scheduling: PERT charts are used to plan and schedule tasks within a project. They help identify the tasks involved in a project, their interdependencies, and the sequence in which they need to be completed. This information is crucial for developing an effective project schedule.
- Resource Allocation: PERT charts help project managers to allocate resources effectively. Managers can assign resources such as personnel, equipment, and materials to each task by analysing the tasks involved in a project and their durations.
- Critical Path Analysis: PERT charts facilitate critical path analysis, which identifies the most extended sequence of tasks that must be completed on time to ensure the project's completion within the given deadline. This helps project managers focus on critical tasks and take corrective action if required.
- Progress Tracking: PERT charts are used to track the progress of a project. By comparing the actual progress with the planned progress, project managers can identify any deviations and take corrective action to get the project back on track.
- Risk Management: PERT charts can be used to identify potential risks and their impact on the project. This helps project managers develop a risk management plan to mitigate potential risks and ensure the project's success.
PERT charts are an essential tool for project managers to plan, schedule, and monitor the progress of their projects. They help ensure that the project is completed within the given time, budget, and scope and that the objectives are achieved.
PERT chart Vs Gantt Chart
PERT and Gantt's charts are two commonly used project management tools that help plan, schedule, and monitor projects. While both charts serve the same purpose, they differ in their approach and the information they provide.
Here are some critical differences between PERT and Gantt charts:
- Network vs Bar Chart: PERT charts display the project as a network diagram of boxes and arrows, where each box represents a task, and each arrow represents the sequence of tasks. On the other hand, display the project as a horizontal bar chart showing each task's start and end dates.
- Task Dependencies: PERT charts show the dependencies between tasks, indicating which tasks must be completed before others can begin. Gantt charts illustrate the jobs' sequence but do not explicitly display task dependencies.
- Critical Path Analysis: PERT charts use critical path analysis to identify the sequence of tasks that must be completed on time to ensure the project's completion within the given deadline. Gantt charts do not explicitly show the critical path, although it can be inferred from the sequence of tasks.
- Resource Allocation: PERT charts can allocate resources effectively by analysing the tasks involved in a project and their durations. Gantt charts also provide information on resource allocation but may need to be more effective in identifying resource conflicts.
- Complexity: PERT charts are better suited for complex projects with many interdependent tasks. In contrast, Gantt charts are better suited for more straightforward projects with few functions.
PERT charts are better suited for complex projects that require detailed planning and critical path analysis. In contrast, Gantt charts are better suited for simpler projects that require a straightforward visual representation of the project schedule.
PERT chart vs CPM
PERT (Program Evaluation and Review Technique) and CPM (Critical Path Method) are two project management techniques used to plan, schedule and manage tasks within a project.
- Application: PERT is primarily used for complex projects that require a detailed analysis of task interdependencies and project timelines. Conversely, CPM is more suitable for projects with many interdependent tasks and a fixed timeline. Here are the critical differences between PERT and CPM:
- Approach: PERT is based on a probabilistic approach, which considers the uncertainties and risks of each task and assigns possible completion times. CPM is based on a deterministic system, which assumes that each job will be completed within a fixed timeframe.
- Task Duration: PERT considers three estimates for each task duration: the optimistic estimate, the most likely estimate, and the pessimistic estimate. CPM only finds the most likely estimate.
- Critical Path: PERT uses a probabilistic approach to identify the critical path, which takes into account the range of possible completion times for each task. CPM uses a deterministic system to identify the necessary way, which assumes that each job will be completed within its most likely duration.
- Risk Management: PERT is useful for risk management because it considers the uncertainties and risks associated with each task. Conversely, CPM is less effective in managing risks because it assumes that each job will be completed within its most likely duration.
PERT and CPM are practical project management techniques with different applications and approaches.
PERT is more suitable for complex projects that require detailed analysis and risk management. At the same time, CPM is more suitable for projects with a large number of interdependent tasks and a fixed timeline.
Considerations for using the PERT chart
PERT (Program Evaluation and Review Technique) charts are valuable tools for planning, scheduling, and managing complex projects. However, several considerations should be taken into account when using PERT charts:
- Task Dependencies: PERT charts are based on identifying task dependencies, which means that each task must be carefully analysed to determine the dependencies. The accuracy of the PERT chart depends on the quality of the identified task dependencies.
- Task Durations: PERT charts rely on estimates of task durations, which can be uncertain or unpredictable. Multiple estimates (optimistic, pessimistic, and most likely) should be used for each task duration to improve accuracy.
- Critical Path: The critical path is the most extended sequence of tasks that must be completed on time to ensure the project's completion within the given deadline. Identifying the critical path is essential for effective project management, and any delay in the critical path tasks will delay the entire project.
- Resources: PERT charts should consider the availability and allocation of resources, including personnel, equipment, and materials. The allocation of resources should be optimized to ensure the project is completed efficiently.
- Risks: PERT charts should consider potential risks and their impact on the project. Risk management strategies should be developed and implemented to mitigate potential risks and ensure the project's success.
- Project Changes: PERT charts should be updated regularly to reflect any changes in the project plan, including changes in task dependencies, durations, or critical paths. Failure to update the PERT chart can result in a project being completed behind schedule or over budget.
PERT charts are valuable tools for project management. Still, careful consideration should be given to task dependencies, task durations, critical paths, resources, risks, and project changes to ensure that the chart accurately reflects the project plan and facilitates effective project management.
When to use the PERT chart
PERT (Program Evaluation and Review Technique) charts are most appropriate for complex projects involving many interdependent tasks and long duration. Here are some situations where PERT charts are handy:
- Significant Projects: PERT charts help manage large projects with many tasks, whereas task dependencies and timelines can be challenging. A PERT chart can help project managers visualize the project, understand the dependencies between tasks, and identify the critical path that must be completed on time to ensure success.
- Complex Projects: PERT charts are handy for managing complex projects with many tasks that must be coordinated and managed effectively. A PERT chart can help project managers identify the most critical tasks and manage them effectively.
- Risk Management: PERT charts can be used for risk management by identifying potential risks and their impact on the project. Project managers can use the PERT chart to develop contingency plans for dealing with risks and ensure that the project stays on track despite unexpected events.
- Time Management: PERT charts can help project managers manage time effectively by identifying the critical path and focusing resources on the tasks most important to the project's success. This can help ensure the project is completed on time and within budget.
- Resource Allocation: PERT charts can help project managers allocate resources effectively by identifying the tasks that require the most resources and focusing those resources on the critical path. This can help ensure that resources are used efficiently and that the project is completed on time and within budget.
How to make a PERT chart
To create a PERT (Program Evaluation and Review Technique) chart, you can follow these steps:
- Identify all the tasks involved in the project: The first step is to identify all the tasks involved. List all the tasks that must be completed to achieve the project's goal.
- Determine the task dependencies: Identify the dependencies between tasks. Determine which tasks need to be completed before others can begin.
- Estimate task durations: Estimate the duration of each task. Use multiple estimates, including optimistic, pessimistic, and most likely, to create a range of possible durations.
- Determine the critical path: Use the estimated task durations and dependencies to determine the critical path, the most extended sequence of tasks that must be completed on time to ensure the project's completion within the given deadline.
- Create the PERT chart: Draw the PERT chart using the task list, durations, and dependencies. A PERT chart is typically drawn as a network diagram, with each task represented as a node and the dependencies between tasks represented as arrows.
- Add milestones to the PERT chart to mark significant events in the project. Milestones can be used to track progress and identify potential problems.
- Update the PERT chart: Update the PERT chart regularly to reflect any changes in the project plan. This can include changes in task dependencies, durations, or critical paths. Updating the PERT chart can help project managers identify potential problems early and adjust the project plan as needed.
In summary, creating a PERT chart involves identifying all the tasks involved in the project, determining task dependencies and durations, identifying the critical path, creating the PERT chart, adding milestones, and updating the chart regularly to reflect any changes in the project plan.